Sunday, 14 November 2010 00:00

The Information Technology Audit

Rate this item
(0 votes)

A picture of a Subway Sandwich Shop

The project was out of control. Within a two-week span, the project manager reported a slide of at least six months. To put the postponement in perspective, the original project plan was a total of nine months. Accusations came from everywhere. The customer complained about the project manager, requirements analysts were frustrated with the customer, the project manager was pushing on his leads to close requirements gathering, there was infighting within the team, and management did fnot know whom to believe. The organization was in mayhem and the only solution was to hire an external auditor to sort out the facts.

The Subway Meeting

I should have realized the degree of the organization's angst when she wanted to meet at a Subway Sandwich shop. No offense to Subway, but it is not the typical venue area for contract negotiation. When I arrived, my friend, we will call her Sara, had dozens of document and numerous three-ring binders strewn across the table. "Thanks for meeting me here. Had I brought you into the office all hell would have broken loose." The periodic panhandler was the only distraction to our three hours of poring over program documentation, status reports, team member profiles, and the core dump on the company politics. Eventually, we concluded that the project could be rescued and that there were plenty of other benefits in a recovery—since this was only one project in a long string of failures, identifying and correcting the underlying problems would be the greatest value.

The First Meeting

A few days later, time and materials contract in hand, I was meeting with corporate directors over breakfast at the Hilton. They explained their concerns about the project. It was obvious that they were frustrated with the situation and were unable to get consistent answers from anyone on the team. By the end of the meeting, they outlined a series of areas they wanted investigated. The primary one was whether the project was following their proprietary project methodology. To help, they had already set up a number of meetings with key stakeholders so I could sift through the mess.

The first meeting with project team members was a quick education in the extent of the problems. This initial meeting was supposed to be a one-on-one meeting with the project manager. However, she could not make the scheduled time, so she suggested I attend her weekly leads meeting. That meeting, too, was difficult to arrange and had been set up as a 'working lunch' in a conference room.

Of the three leads, only two attended; both were obviously annoyed as they munched on their lunch between verbal jabs. They tried in vain to get the project manager to make the decision or delegate the authority so they could put bounds around scope to close requirements gathering. The project manager kept asking her lieutenants to complete the requirements; however, she would not give them the authority to limit scope. The interplay was viciously circular making the meeting frustratingly ineffective. Everyone left exasperated.

Project Health Check

Ask for more info above, or if you are convinced, just add it to your cart..

The Endemic Problem

The interviews continued including samples from the C-Suite to the testers. The further the person was from the C-Suite, the more bizarre their comprehension of the project's goal. To my amazement, though, the element of the project that had the least consensus throughout the organization was who would be the system's primary user. The team was trying to build a tool and was misaligned on who would eventually use the product.

The project's archive held the answer. They clearly showed who would be the end user; however, the project charter never defined them. I asked the director of the PMO if the approved chapter was complete. She replied, "It has all the sections we require." When pressed further she relented that the people in the PMO did lacked the business knowledge to know if the content was appropriate. No level of process, proprietary or open, will overcome lack of knowledge.

Finding the Root Cause

The story could continue. Senior management insisted the project was the problem; however, upon identifying the end user, the project ran fine and achieved its goals. People were following the internally designed processes, but no one was validating that the content of the deliverables was appropriate. Poor data fed process steps and deliverables had no value. Garbage in, garbage out.

The culture placed process above content. The approach to running projects, managing people, guiding communications, and making decisions was faulty. The only solution was to have someone outside the organization—objective and unbiased—analyze the organization. Internal auditors are at a severe disadvantage. They are part of the culture, politics, and finger pointing.

External Audits

Although routinely done in accounting, Information Technology (IT) groups rarely request external audits. This may be due to the maturity of accounting (many credit its genesis to Luca Pacioli in the fifteenth century with references to auditing even earlier) and the relatively young IT discipline (less than sixty years). Speculation on the reasons may be fun, but are irrelevant. The solution is to create an open culture that embraces the audit. Not just of projects, but of all IT operations. Recently I was involved with an IT audit. A client brought us in to help with their compliance. As with project audits that I have conducted, the external auditor sets the stage for a smoother running operation and a culture acceptant of criticism as a constructive tool.

Read 9194 times

Related items

  • Filling Execution Gaps: How Executives and Project Managers Turn Corporate Strategy into Successful Projects
    What Filling Execution Gaps Covers

    Filling Execution Gaps

    by Todd C. Williams
    ISBN: 978-1-5015-0640-6
    De G Press (DeGruyter), September 2017

    Project alignment, executive sponsorship, change management, governance, leadership, and common understanding. These six business issues are topics of daily discussions between executives, middle management, and project managers; they are the pivotal problems plaguing transformational leadership. Any one of these six, when improperly addressed, will hex a project's chances for success. And, they do—daily—destroying the ability companies to turn vision into value.

    Check it out on Amazon or the Filling Execution Gaps website

    Without the foundation of a common understanding of goals and core concepts, such as value being critical to success, communication stops and projects fail.

    Without change management, users fail to adopt project deliverables, value is lost, and projects fail.

    Without maintaining alignment between corporate goals and projects, projects miss their value targets and projects fail.

    Without an engaged executive sponsor, scope increases, goals drift, chaos reigns, value is lost, and projects fail.

    Without enough governance, critical connections are not made, steps are ignored, value is overlooked, and projects fail.

    Too much governance slows progress, companies cannot respond to business pressures, value drowns in bureaucracy, and projects fail.

    Without strong leadership defining the vision and value, goals are not set, essential relationships do not form, teams do not develop, essential decisions are not made, and projects fail.

  • Filling Execution Gaps: Building Success-Focused Organizations

    Executives define vision, strategy, and goals to advance the business. Projects enable companies to meet those goals. Between strategy and projects, there is a lot of work to be done—work that lays the foundation for project and operational success. Through experience and research, six common gaps exist in organizations that inhibit project success—an absence of common understanding, disengaged executive sponsors, misalignment with goals, poor change management, ineffective governance, and lackluster leadership.

  • Get Recognized as a Leader: Four Core Leadership Actions

    Leaders make decisions. This requires a core set of actions to gather the best information, hear out the concerns of others, and making a decision that everyone will follow—even if there is not unanimous agreement with the decision. Although there are hundreds of actions leaders must take, there are four core actions that all great leaders do—listening, dialog and discussion, selling a vision, and eliminating blame. This session will discuss those actions in a roundtable format that we call a "What Would You Do?" session. In these sessions, the presenter acts as a moderator spending 10 to 15 minutes per topic working with the audience talking about what the action is, how to best do it, and hearing from the group on how they have carried out the action. This brings significant audience interaction, involvement, and broader education. 

  • Build Your Leadership Style: Six Leadership Strategies

    Salespeople, Project managers, and business leaders, to name a few, need to change their leadership style for every situation. Situational leadership is more important for these roles than nearly any other role in an organization. Central to this leadership style is commanding the six core strategies—directive, expert, consensus, engaging, coaching, and affiliative. These sets leaders the foundation for building the most appropriate leadership style for the conditions surrounding the current events, people in the room, and external conditions. In this roundtable session, which we refer to as a "What Would You Do?" format, the audience debates the use of each strategy as the presenter poses various conditions and dilemmas that face leaders daily. This creates an educational, interactive and entertaining presentation that builds cohesiveness in your group and relationships that last long after your event.

  • Kill The White Knight

    There is a reason we hesitate to teach classes on fixing failing projects. Many a cynic feels that we simply do not want to teach our trade, however, our reason is far nobler—we should be teaching prevention rather trying to create white knights to save the day. It is the same philosophy as building a fence at the cliff's edge rather than an emergency room at its base. Our language is replete with idioms telling us to look past the symptoms and address problems at their root cause. 'An ounce of prevention versus a pound of cure' or 'a stitch in time saves nine.' Please, feel free to supply your own in the comments. Unfortunately, most of our businesses loathe this philosophy, waiting to address an issue until it is irrefutably broken.

Leave a comment

Filling Execution Gaps

Available Worldwide

Filling Exectution Gaps cover

Filling Execution Gaps is available worldwide. Below are some options.

 

PG DirectLogo
Limited Time Price $20.99
Amazon logo
Book or Kindle
Flag of the United States Canadian Flag Flag of the United Kingdom Irish Flag Deutsche Flagge
Drapeau Français Bandiera Italiana PRC flag
Japanese flag
Bandera de España
Flag of India
Bandera de México
Bandeira do Brasil
Flag of Australia
Vlag van Nederland
DeG Press Logo
Barnes and Noble Logo
Books a Million Logo
Booktopia Logo
Worldwide: Many other
book sellers worldwide.

Rescue The Problem Project

Internationally acclaimed

Image of RPP

For a signed and personalized copy in the US visit the our eCommerce website.

Amazon logo
Buy it in the United States Buy it in Canada Buy it in the United Kingdom
Buy it in Ireland Buy it in Germany Buy it in France
Buy it in Italy Buy it in the PRC
Buy it in Japan